WIMAP PROJECT
France
Rendered Services
Electrical and Instrumentation Works (units 100/200/300).
Project Description
Construction of two new 200/300 units and revamping of an existing unit (unit 100).
Work carried out in two electrical rooms.
Approximately 55,000 man hours were required to carry out this work.
Engineering
Detailed engineering of the cabinets to be supplied (Qty: 50 units).
Procurement
Supply of false floors Qty: 60 m2
Supply of cabinets Qty: 20units
Supply of main cable trays Qty: 3850 metres
Supply of secondary cable trays Qty: 3550 metres
Supply of multi-cables / power / single Qty: +-150km
Supply of Fire&Gas equipment Qty: 70units
Supply of CCTV Qty: 6un
Supply of street lighting Qty: 85un
Supply of instrumentation material Qty: 450un
Pilot air supply Qty: 1500mts
Supply of Jb’s Qty: 60un
Supply of electrical tracing (+-3500ml of tape)
Supply of lightning conductors Qty: 400mts
Construction
False floor installation
Installation of cabinets.
Installation of cable trays, cable routing and connections
Installation of instruments
Fire & gas equipment panel installations
CCTV installations
Analyser installation
Lighting installation
Electrical tracing installation
Pilot air installation
Lightning conductor installation
Revamping of unit 100
Quantities Installed
Cabinet installation. Qty: 35units
Installation of main cable routes Qty: 7550mts
Cable routing Qty: 150km
Installation of instruments Qty: 450units
Installation of junction boxes Qty: 60un
CCTV/panel installations Qty: 6un
Fire & gas equipment installation Qty: 70un
Electrical tracing installation Qty: 3100mts
Lighting/post installation Qty: 85un
Client:
- INEOS
End of Contract:
- 2021