Tandem, New HMD

France

Project Description

TCPI played a very important and decisive role in the completion of the Tandem Project, located in Chalampé, France.
Taking into account the scope of E&I, the great contribution of the workers coordinated by an excellent TCPI team led the project to make an enormous contribution to the 2 million safe working hours and the high quality of the construction work presented.

In summary, the north and south storage tanks were substantially completed and released for commissioning in May 2024.

Construction

The mechanical completion and handover of the North and South tank farms were completed in July 2024.

Distillation: Completed on 2 September 2024.

Synthesis: Completed on 20 September 2024.

Overall mechanical completion of the project: 27 September 2024.

Start-Up: Distillation: Completed on 10 January 2025; Synthesis: Completed on 31 January 2025.

Client:

  • BASF

End of Contract:

  • 2023-2024