Phoenix Project- EPC2 Boiler 14
La Mède, France
Rendered Services
E & I erection; Pre Commissioning.
Project Description
Procurement
Cable trays
Electricity, Instrumentation Cables
Distribution of the instrument air network
Construction:
Installation of the main and secondary cable trays
Cable running in unit
Installation of electrical and control panels
Connection of electrical cables, instrumentation
Loop test
Installed Quantities
Cable trays: 1,000 m
Electrical Cable: 4,000 m
Instrumentation Cables: 7,500 m
Instruments: 80 item
JB: 30 units
Client:
- TOTAL / CORETEC
End of Contract:
- 2018
Project Amount:
- 200 K€