PROJECT TYVEK® LINE 8
Luxemburg
Rendered Services
TCPI carried out the installation, construction and assembly of cable trays as well as all the instrumentation.
Project Description
Installation of aluminium main cable trays.
Use of isometrics to install main cable trays.
Mobilisation
No. of hours planned: 85,000 hours
No. of hours worked: 142 000h
Peak on site: 100 people
Installation
Quantities installed
Installation of main cable route
Total installed: 3.5Km
Installation of secondary cable route
Total installed: 5.5Km
Cable crossing
Total installed: 320 Km
Electrical tracing installation
Total installed: 5300 ml
Cable connections
Total: 11 100 units
Instrument installation
Total installed: 2200 units
Tubing installation
Total installed: 18 Km
25 mm: 500 ml
22 mm: 115 ml
18 mm: 2560 ml
12 mm: 6770 ml
8 mm: 3340 ml
6 mm: 3450 ml
Client:
- CLEMESSY (for DuPont ™)
End of Contract:
- 2023