TCPI provided the set of equipment and services (EPC), included in the provision of the Safety and Electricity Installation.
Project Description
The project consists of 4 Horizontal Kaplan turbines, grouped with 9.1MVA / 10kV alternators each, to connect to the national network via a 10/60kV substation.
Procurement/Installation
The work scope includes material and accessories complementary supply to the installation and the execution of the installation work, comprising the following stages:
- Engineering;
- Validation of Technical Specifications and Requisitions of the equipment to be supplied;
- Procurement;
- Electrical and Instrumentation Installation;
- Training;
- Commissioning and Start up
Intervention Areas: Power Station; 60kV Substation; Loading Chamber; Dam
Client: