TCPI provided instrumentation and electrical work in the B3 building and electrical work in the B5, B6 and Piperack buildings.
Issuing and updating electrical panel drawings.

Project Description

The project consisted of installing E&I in the 2nd phase of Building B3, comprising a Hydrogenerator, Dryer, 2 reactors and other equipment, involving electrical assembly and the supply and alteration of existing panels, and the assembly of the associated instrumentation.

HH realised – 12,680
Total number of people in Pico – 25
Execution time – 12 months

Procurement

Supply and installation of electrical panels / alterations to existing panels
Supply and installation of cable trays
Supply, installation and connection of cables
Installation of instruments
Testing / commissioning
Issuing as-built electrical panels

Construction

Opening and closing cable trenches
Cable supply and installation
Supply and installation of cable trays
Supply and installation of flanges for installing levels

Quantities Installed

Cable trays – 1,175m
Instrumentation cables – 13,900m
Power cables – 6,000m
Instruments: 570Un
LV switchboards – 9units

Client:

  • HOVIONE FARMACIÊNCIA, S.A.

End of Contract:

  • 2022