Project Description
Since 2018, TCPI has been involved in this Project to build two new vertical storage tanks for Gasoline and Diesel for heating, with a storage capacity of 4,000m3 up to a maximum of 19,000 m3.
Rendered Services
In this project, TCPI was the “Executing Entity”, that is, the “General Contractor”, and as such responsible for:
– Detail engineering;
– Supply and Erection of all Mechanical works;
– Supply and Erection of all Piping work;
– Supply and Erection of all Civil Construction works;
– Supply and Erection of all Electricity works;
– Supply and Erection of all Instrumentation works;