EO2 PROJECT_E&I INSTALLATION
Antwerp, Belgium
Rendered Services
E & I construction work.
Total direct man-hours spent: 200,000 hours.
Project Description
Construction
The E&I construction part of the EO2 Project had its greatest impact on the following phases and activities:
➢ Pre dressing of 7 columns with: cable trays, lighting poles and luminaires, instrument hook ups, JB’s, cables and connections;
➢ Substation installation including: MV transformers, MV switchgear, MV cables and connections, LV CCM panels, UPS and battery chargers, DCS panels and consoles, sorting and interface cabinets, lighting system, earthing system including lightning and surge arrester system, interconnection cables between substation panels and equipment, etc;
➢ Construction on site: prefabrication and installation of supports, installation of: cable trays, panels, LV and instrumentation cables, lighting poles and devices, earthing system, power boards, instrumentation JB, instrument connections, fire detection and fighting system, gas detection system, cctv system, analyser piping and cabling installations, calibration and installation of instruments, etc;
➢Circuit testing and verification: all cable tests (continuity and megger tests), equipment inspections and tests, motor tests, lighting inspection and tests, earthing system tests, circuit verification, etc;
➢Commissioning: assistance with commissioning and start-up.
Procurement
➢Installation of main cable trays (ladder trunking 200, 400, 600) – 9,500m
➢Installation of secondary cable trays (50, 100) – 18,500m
➢Installation of equipment – 800un luminaires, 850un junction boxes
➢Installation of equipment – Socket boxes 65un
➢Installation of equipment – JB’s instrumentation 580un
➢Installation of equipment – JB’s power 200un
➢Installation of equipment – Local controls 38un
➢Installation of equipment – MCC’s 75un
➢Installation of equipment – Frequency inverters 20un
➢Installation of equipment – Battery chargers and UPS 25un
➢Installation of equipment – Batteries 350un
➢Installation of equipment – Lighting boards – 7un
➢Installation of equipment – Tracing boards 5un
➢Installation of equipment – Marshaling 19un
➢Installation of equipment – Lightning arrester 11un
➢Installation of cables (power, control, signal, F&G, fibre optics) – 306,000m
➢Cable connection (power, control, signal, F&G) – 11,000un
➢Installation of electrical tracing cables – 12,500m
➢Electric tracing cable connection 1800un
➢Installation of JB’s electric tracing 350un
➢Hookup – impulse and air lines 7,700m
➢Execution of Hookup’s – Installation of instruments 2,200un
➢Execution of Hookup’s – Calibration of instruments 1,500un
➢F&G system installation – 580un
➢Loop testing 3900un
Client:
- BASF
End of Contract:
- 2023