HEXCEL Instrumentation Project

France, Lyon

Rendered Services

Instrument installation, cable and earth paths installation, cables and connections installing as well as electrical tracing.

Project Description

Cable installing work and connections in technical outdoor locations.
Installation of instrumentation on all the work process units (about 5 zones: Carbone / Dope Tower / Utility / Unloading / Polymer).
Electrical tracing installation.

Construction/Erection

Working hours: Aprox. 30,000 man hours
Total People at Peak: 50
Work Execution Time: 8 Months

Installed Quantities

Cable trays: 127KM
Electrical Tracing: 20KM
Instruments: 560un
Junction Boxes: 200un

Client:

  • BOUYGUES

End of Contract:

  • 2018

Project Amount:

  • 1.300 K€