CPMZ Project – Booster Pumps

Beira, Mozambique

Rendered Services

TCPI provided Equipment Procurement, Electrical Installations and Instruments Construction of Booster Pumps at TOTAL’s Fuel Storage facilities in Beira, Mozambique.

Project Description

Procurement

Instruments; Derivation Boxes; Electric Frames; Lighting; Control buttons for motors; Electrical and instrumentation cables; Primary and secondary cable trays.

Construction/ Erection

Construction activities for installation with the use of approximately 15,000 man hours, with 23 workers at work peak.
Electricity; Instruments; Commissioning and initial installation start-up.

Installed Quantities

Cable trays: 850 m
Cable Control & Instrument: 800m
Instruments: 4 units
Junction Boxes: 5 units
Electrical Equipment: 8 units
Electric Frames: 2 units
Electrical Cable: 4,800 m
Earth cable: 200m