Services provided

TCPI INTERNACIONAL provided Equipment Procurement services within the Installation scope. It performed Instrumentation and Installation of: cables, cable trays, electrical panels; Lighting; Tests; Pre-Commissioning and Commissioning at Lisnave shipyards in Setúbal, Portugal.

Project Description

The project consisted of electrifying and installing instruments on two floating platforms for the production of wind energy, to be anchored offshore at open sea.

WINDFLOAT ATLANTIC Project is the first marine wind farm in Portugal and the first floating wind farm in Continental Europe.

Construction

Supply and installation of electrical energy panels

Supply and installation of electrical outlets

Supply and installation of lighting equipment

Supply and installation of cable trays

Supply and installation of electrical cables

Supply and installation of instrumentation cables

Supply and installation of communication cables

Supply and installation of instruments

Tests and pre-commissioning

 

Working hours: Approx. 8.000 hours / Man

Total People at Peak: 15

Work Execution Time: 20 Weeks

 

Installed Materials:

Cable Trays

Electric cables

Control, common and instrument cables

Junction Boxes

CE Outlets

Instruments

Distribution QE

Luminaires