Anagold – Çöpler Sulphide Expansion Project

Erzincan, Turkey

Rendered Services

TCPI INTERNACIONAL provided the following services: Labor supply for Instrumentation and Electricity works in the Çöpler Sulphide Expansion Project at the Anagold Çöpler gold mine in Erzincan, Turkey.

Project Description

Provision of technical labor

TCPI INTERNACIONAL provided 1 supervisor, 4 team leaders, 30 electricians and 6 instrument technicians to carry out electrical and instrumentation works for Anagold.

The works included:

Termination and testing of LV and MV cables
Installation and testing of lighting systems
Connections and Control Room Automation Testing
Loop Testing

Client:

  • ANAGOLD

End of Contract:

  • 2018

Project Amount:

  • 700 K€